Aug 11, 2025

Town resumes decommission of abandoned Mackie Dam

Ladysmith, BC — The Town of Ladysmith is moving ahead with the decommission of the abandoned Mackie Dam after an 11-month pause to protect salmon spawning in Holland Creek.

Removal work, which is being carried out by Spider Mountain Excavators (SME), will begin on August 14 and is expected to conclude on September 16.

During this time, a 1.5-kilometre section of the North Loop of the Holland Creek/Heart Lake Trail will be closed to the public. A detour route is in place via Colonia Drive, Malone Road, and 6th Avenue to accommodate trail users.

“The decommissioning of the abandoned Mackie Dam is an important step in protecting the long-term health of Holland Creek," says Mayor Deena Beeston. We know the temporary closure of part of the Holland Creek Trail may cause inconvenience, and we’re grateful for the community’s patience and understanding during this time.”

Mackie Dam—sometimes called the Mackie Road Dam—is a 3.8-metre-high and 12-metre-wide abandoned timber crib structure dam located on Holland Creek near the intersection of the Holland Creek Trail and Mackie Trail. The dam is being removed following a 2023 recommendation from BC Dam Safety.

In September 2024, the Town decided to postpone the removal of Mackie Dam after the Department of Fisheries and Oceans (DFO) and the Ministry of Water, Land, and Resource Stewardship (WLRS) provided new information which indicated that the timing of the removal posed a significant threat to salmon in Holland Creek.

The project is being funded with a $2.75 million grant that the Town received from the provincial government to remediate three weirs along Holland Creek, including the Mackie Dam. The decommissioning of Mackie Dam is expected to cost an estimated $600,000.

Mackie Dam Removal Holland Creek Trail Closure Map

Background

The Mackie Dam, also referred to as the Mackie Road Dam, is a 3.8-metre-high and 12-metre-wide abandoned timber crib structure dam located on Holland Creek near the intersection of the Holland Creek Trail and Mackie Trail.

The Town believes the dam was built more than 70 years ago by the Wellington Collieries Company for coal mining.

At some point over the past 70 years, although it isn’t exactly clear when, the Town of Ladysmith became the dam’s owner through ownership of the surrounding land.

Why is the Town decommissioning the dam now?

Dam Safety BC requested that the Town of Ladysmith undertake a review of the dam with a professional engineer. The review was completed in the fall of 2023 and found that the dam does not meet current safety standards, and that downstream hazard exists. The dam was also found to be a fish barrier.

What does the decommissioning process look like?

The removal of Mackie Dam will consist of mechanical removal of the impounded sediment, the transport of sediment offsite, removal of the dam structure itself, and restoration of the area. Spider Mountain Excavators (SME) will first create a barrier on the south side of Holland Creek to direct the water flow to the north side of the creek, which will help keep the work area dry. Once work is finished on the south side, the barrier will be moved to the north side and SME will continue with the excavation and dam removal.

A spider excavator, which will handle all instream works including the diversion installation, excavation, demolition of the dam concrete structure and removal of dam timber structures, as well as a long-reach excavator and an articulated dumper will be used to complete the work. A small number of trees are required to be removed during the decommissioning. All removed trees will be offered to Stz'uminus First Nation.

What impact will there be to the trail network?

A 1.5-kilometre section of the North Loop of the Holland Creek Trail/Heart Lake Trail will be closed to the public. A detour route has been established along Colonia Drive, Malone Road and 6th Avenue for trail users. Closures of the south section of the Holland Creek Trail are not anticipated, unless a safety concern is identified.

Is there a risk to any infrastructure during the removal process?

There is little if any infrastructure at risk from decommissioning Mackie Dam. There is an important waterline, which will be clearly identified and protected during the removal process. The decommissioning of the dam will not permanently impact recreation facilities, businesses, or property value.

What happens once the dam is removed?

Upon removal of the dam structure and sediment, remediation of the creek bed will be performed. The contractor will use natural sediment to blend the existing creek channel with the construction disturbance and plant natural species along the creek banks where possible. There is some bedrock outcropping in the area, which will be left as much in the original condition as possible. Fish barriers will be removed and replaced with deadwood and pools to provide fish habitat.

What about the other abandoned dam on Holland Creek?

There is another abandoned dam upstream of Mackie Dam (Colonia Dam), as well as the Town’s water intake dam even further upstream (Holland Creek Intake). Both dams require work to be compliant with dam safety regulations, although they are a lower priority. Work for these dams will likely be completed in 2025 or 2026. This work will include concrete repairs, stream bed improvements, signage, fencing, and flood erosion protection.

For the latest news and updates, visit the Town’s website at www.ladysmith.ca, as well as Facebook and Instagram.

The Town of Ladysmith respectfully acknowledges that we gather and work on the unceded territory of the Stz'uminus First Nation, the traditional keepers of this land.

-30-

Media Contact
Nicholas Pescod
Communications & Engagement Specialist
npescod@ladysmith.ca
250-268-0606

Related Images:
Mackie Dam
The Town of Ladysmith is moving ahead with the decommission of the abandoned Mackie Dam after an 11-month pause to protect salmon spawning in Holland Creek.